“Remeks” started the construction of the crossing bridge on the River Dinyeper in Kiev Ukraine at the beginning of 2005. Total length of the bridge is 3500 meters, 47 meters in width, with the addition of the crossings and the viaducts, it consists of 79000 tons of steel.
During the construction of the steel structures of the bridge, “GOST” standards were used as the main standardization:
- VSN 188-78 (Mechanical Instructions for the welded members of bridge steel constructions);
- SNIP 3.06.04-91 “Bridges and Pipes”;
- DBN B.2.3-14 “Bridges and Pipes. Project Design Rules”;
- SNIP III-18-75 “Project Works and Acceptance Rules”.
Steel constructions consist of box beams (Closed or U shaped), orthotropic panels, outer consoles, montage plates, bolts, nuts and such members. Manufactured constructions were pre-assembled before the transportation to the client. Therefore, it is possible to control the geometrical parameters of the complete structure.
In addition, total of 6000 m² molds which were used to make the concrete bridge legs, were manufactured by “Remeks”.
For all the constructions mentioned above, completely in house built by our engineers, specialized REGAMAK ® machinery was used.
Regarding to the completion of the bridge steel construction agreement, “South-West Government Railroads of Ukraine” gave “Remeks” superior work and success medal. “Remeks” received 140.000.000 USD valued work completion certificate, apostilled by the Ukrainian Foreign Ministry.